HR/SA Schedule for Tru64 to HPUX Upgrade

The details below provide information regarding the HR/SA Schedule for the Tru64 to HPUX Upgrade Project.



HR/SA Schedule:
    • March 2 , 2010, 11:00 AM to Noon, SURC 201: Kickoff Meeting for HR/SA
    • March 2 , 2010: Freeze of FSPRD/CSPRD data for creation of CSTSTX/FSIB and refresh of CSTST
    • March 5, 2010, thru March 7, 2010: HR/SA Phase 1 CSTSTX Database Technical Upgrade (complete)
    • March 15 2010: HR/SA Phase 1 Data Validation (complete)
    • March 16, 2010, thru April 28, 2010: HR/SA Phase 1 Process Testing
    • 4:00 PM on April 30 , 2010, thru May 2, 2010: HR/SA Phase 1 Go Live for CSPRD/CSRPT
    • April 19, 2010, thru April 23, 2010: HR/SA Phase 2 FSTST Application Technical Upgrade
    • May 2, 2010: Freeze of FSPRD/CSPRD data for refresh of FSIB and CSTST
    • May 11, 2010, thru June 11, 2010: HR/SA Phase 2 FSTST Application Testing
    • June 20 , 2010: HR/SA Phase 2 CSPRD/CSRPT Go Live


Project Staff:
Contact Information

Tru64Unix Project
Email: jonesk@cwu.edu
Central Washington University 400 E. University Way, Ellensburg WA 98926 This Site Optimized For Newer Browsers.
Go back to Central's main page