HR/SA Schedule:
  • March 2 , 2010, 11:00 AM to Noon, SURC 201: Kickoff Meeting for HR/SA
  • March 2 , 2010: Freeze of FSPRD/CSPRD data for creation of CSTSTX/FSIB and refresh of CSTST
  • March 5, 2010, thru March 7, 2010: HR/SA Phase 1 CSTSTX Database Technical Upgrade (complete)
  • March 15 2010: HR/SA Phase 1 Data Validation (complete)
  • March 16, 2010, thru April 28, 2010: HR/SA Phase 1 Process Testing (complete)
  • 5:00 PM on April 30 , 2010, thru May 2, 2010: HR/SA Phase 1 Go Live for CSPRD/CSRPT (complete)
  • April 26, 2010, thru May 10, 2010: HR/SA Phase 2 CSTST Application Technical Upgrade
  • May 2, 2010: Freeze of FSPRD/CSPRD data for refresh of FSTST and CSTST
  • May 11, 2010, thru June 17, 2010: HR/SA Phase 2 CSTST Application Testing
  • June 20 , 2010: HR/SA Phase 2 CSPRD/CSRPT Go Live


Project Staff:
Contact Information

Tru64Unix Project
Email: jonesk@cwu.edu
Central Washington University 400 E. University Way, Ellensburg WA 98926 This Site Optimized For Newer Browsers.
Go back to Central's main page