The details below provide information regarding the HR/SA Schedule for the Tru64 to HPUX Upgrade Project.
HR/SA Schedule:
- March 2 , 2010, 11:00 AM to Noon, SURC 201: Kickoff Meeting for HR/SA
- March 2 , 2010: Freeze of FSPRD/CSPRD data for creation of CSTSTX/FSIB and refresh of CSTST
- March 5, 2010, thru March 7, 2010: HR/SA Phase 1 CSTSTX Database Technical Upgrade (complete)
- March 15 2010: HR/SA Phase 1 Data Validation (complete)
- March 16, 2010, thru April 28, 2010: HR/SA Phase 1 Process Testing
- 4:00 PM on April 30 , 2010, thru May 2, 2010: HR/SA Phase 1 Go Live for CSPRD/CSRPT
- April 19, 2010, thru April 23, 2010: HR/SA Phase 2 FSTST Application Technical Upgrade
- May 2, 2010: Freeze of FSPRD/CSPRD data for refresh of FSIB and CSTST
- May 11, 2010, thru June 11, 2010: HR/SA Phase 2 FSTST Application Testing
- June 20 , 2010: HR/SA Phase 2 CSPRD/CSRPT Go Live
|