Facilities Management: Construction News |
Student Village South Residence HallThis page last updated 11/13/2007 Project Scope and SummaryDesign and construct a new residence hall to replace beds lost with Courson/ Muzzall. The selected site is at the Northwest corner of Dean Nicholson Blvd. and Alder. Project Schedule
StatusArchitect/ Engineer has been selected. Design Development phase in progress and expected to be complete by December 2007. Construction documents are expected to be complete for April 2008 bidding. Occupancy is expected for Fall 2009. Contract and Project Management InformationProjected Project Budget: $ 38,000,000.00 DetoursNo detours at this time. Utility OutagesNo outages at this time. |
|||||||||||
|
Contact Information
Facilities Management 400 E. University Way Ellensburg, WA 98926 (509) 963-3000 email: winegarm@cwu.edu |